Serra Dourada

Serra Dourada Project

Serra Dourada

Serra Dourada Project


Timeline

  • June/2023
    Lot obtained at the ANEEL transmission auction (01/2023)
  • January/2025
    Signing of the Memorandum of Understanding with the State Government of Bahia to reinforce the strategic relevance of the project for the state
  • February/2025
    Obtaining the first Preliminary Environmental License (LP) for the 500 kV Buritirama - Barra II Transmission Line
  • August/2025
    Issuance of the Installation License by IBAMA for the 500 kV Barra II – Correntina – Arinos 2 section and for the Correntina Substation
  • January/2026
    Installation License issued by INEMA for the 500 kV Buritirama – Barra II section
  • May/2026
    Installation License issued by INEMA for the 500 kV Juazeiro III – Campo Formoso II – Barra II transmission line section
  • March/2029
    Energization (deadline set by ANEEL)


Contact ISA ENERGIA BRASIL

Image of a person smiling, sitting at a table in front of a computer.

Are you interested? Please contact us.
We are available if you have any questions, suggestions or any other topic you want to discuss with us.

Contact us
FALE
com nosso time
de atendimento