Timeline
- June/2023
Lot obtained at the ANEEL transmission auction (01/2023) - January/2025
Signing of the Memorandum of Understanding with the State Government of Bahia to reinforce the strategic relevance of the project for the state - February/2025
Obtaining the first Preliminary Environmental License (LP) for the 500 kV Buritirama - Barra II Transmission Line - August/2025
Issuance of the Installation License by IBAMA for the 500 kV Barra II – Correntina – Arinos 2 section and for the Correntina Substation - January/2026
Installation License issued by INEMA for the 500 kV Buritirama – Barra II section - May/2026
Installation License issued by INEMA for the 500 kV Juazeiro III – Campo Formoso II – Barra II transmission line section - March/2029
Energization (deadline set by ANEEL)