Riacho Grande

Riacho Grande Project

Riacho Grande

Riacho Grande Project


Timeline

  • June/2020
    Award of the lot in the ANEEL transmission auction (01/2020)
  • June/2023
    Obtaining the installation environmental license
  • June/2023
    Start of construction of the underground transmission line
  • April/2024
    Groundbreaking ceremony for the São Caetano do Sul Substation
  • February/2025
    Obtaining the Operating Environmental License
  • April/2025
    Energization of the 345 kV Ibiúna – Tijuco Preto overhead transmission line
  • November/2025
    Start of commercial operation (5 months ahead of the ANEEL deadline)
  • March 2026
    Energization and inauguration of the project