Timeline
- June/2020
Award of the lot in the ANEEL transmission auction (01/2020) - June/2023
Obtaining the installation environmental license - June/2023
Start of construction of the underground transmission line - April/2024
Groundbreaking ceremony for the São Caetano do Sul Substation - February/2025
Obtaining the Operating Environmental License - April/2025
Energization of the 345 kV Ibiúna – Tijuco Preto overhead transmission line - November/2025
Start of commercial operation (5 months ahead of the ANEEL deadline) - March 2026
Energization and inauguration of the project