Timeline
- June/2022
Awarding of the lot in the ANEEL Transmission Auction (01/2022) - July/2024
Obtaining the Installation and Operating Environmental Licenses from the State Environmental Foundation - November/2024
Completion of the largest green bond issuance of 2024 (BRL 1.8 billion) to finance the Piraquê Project - November/2024
Start of construction with the erection of the first transmission tower - February/2025
Construction of the 1,000th transmission tower - November/2025
Block 1 energization - March/2026
Block 2 energization - June/2026
Block 3 energization and project completion, achieved 16 months ahead of the ANEEL deadline (September 2027)