Piraque

Piraquê Project

Piraque

Piraquê Project


Timeline

  • June/2022
    Awarding of the lot in the ANEEL Transmission Auction (01/2022)
  • July/2024
    Obtaining the Installation and Operating Environmental Licenses from the State Environmental Foundation
  • November/2024
    Completion of the largest green bond issuance of 2024 (BRL 1.8 billion) to finance the Piraquê Project
  • November/2024
    Start of construction with the erection of the first transmission tower
  • February/2025
    Construction of the 1,000th transmission tower
  • November/2025
    Block 1 energization
  • March/2026
    Block 2 energization
  • June/2026
    Block 3 energization and project completion, achieved 16 months ahead of the ANEEL deadline (September 2027)

Contact ISA ENERGIA BRASIL

Image of a person smiling, sitting at a table in front of a computer.

Are you interested? Please contact us.
We are available if you have any questions, suggestions or any other topic you want to discuss with us.

Contact us
FALE
com nosso time
de atendimento