Minuano

Minuano Project

Minuano

Minuano Project


Timeline

  • December 2019
    Award of the lot in the ANEEL transmission auction (02/2019)
  • July 2023
    Obtaining the Installation Environmental License issued by the State Foundation for Environmental Protection (Fepam) of Rio Grande do Sul
  • March 2024
    Obtaining the Operation License for the Caxias Norte Substation
  • September 2024
    Obtaining the Operating License issued by the State Foundation for Environmental Protection (Fepam), of Rio Grande do Sul, for the energization of two transmission lines - sectioning of 525 kV Caixas – Caxias Norte – Itá and the 230 kV Caxias Norte – Caxias 6, which are 35 kilometers long, passing through the municipalities of Caxias do Sul, Flores da Cunha and Farroupilha
  • November 2024
    Energization of the Minuano Project five months ahead of the deadline established by the National Electric Energy Agency (Aneel)


Contact ISA ENERGIA BRASIL

Image of a person smiling, sitting at a table in front of a computer.

Are you interested? Please contact us.
We are available if you have any questions, suggestions or any other topic you want to discuss with us.

Contact us
FALE
com nosso time
de atendimento